Eau Claire County Building Project
Key Construction Dates
2010
- July 26: Construction of law enforcement parking garage begins.
- August 23: Construction of north parking lot begins.
- August 30: Delivery and installation of building precast concrete.
- September 16: Waterproof Parking Deck
- September 17: Precast Installation Complete
- September 23: North Parking Lot Opens (pending weather / AT&T)
- September 27: First Avenue Shut Down & Tie-ins (1 week)
- September 30: Concrete Topping @ Top Deck
- October 8: Exterior Concrete Walks/Drive @ Garage
- October 13: Second Ave. Shutdown, Utility Tie-Ins
- October 15: Lake Street Tie-Ins, Future Second Ave. Utiilty Work Complete
- October 18: Jail Site Work and Foundation Bid Package Out to Bid
- October 18: Landscaping @ Parking Structure
- November 3: Jail Site Work & Foundation Bid Approval by County Board
- November 5: Law Enforcement Garage Open
- November 8: Jail Site Fenced for Construction / 2nd Avenue Closed
- November 8: Jail Site Utilities / Entrances Temporarily Re-routed
- November 15: Jail/Courthouse Entrances Opened
- November 15: Jail Site/Foundation Construction Start
- November 22: Jail Vibropiers Process Begins
- December 23: Jail & Remodel Plans Out for Bid
- December 31: Jail Vibropiers Completion
2011
- January 11: Precast Erection Bids Due
- January 18: Pre-Bid Meeting/Walk Through
- February 3: Jail & Remodel Bids Due
- February 8: Committee Review of Bids
- February 15: County Board Review of Bids
- February 17 - May 4: Jail Precast Frame Start
- April: Jail Building Shell
- April-October: Courthouse - Existing Entrance/Board Room Addition
- Summer 2011: Second Ave./First Ave. Street Reconstruction (pending City of Eau Claire)
- November 2011: Jail Exterior Finishes/Parking Lot Complete
2012
- May: Jail Occupancy
- June: Courthouse / Phase 3 Remodel
2013
- January-June: Communication Center Remodel
- December: Courthouse Project Completion
|