New Construction of Jail & Law Enforcement Center and Remodeling of Courthouse
Concepts of a new jail Concept site plan NIC Report Organization Chart Proposed Project Schedule
Newsletters and Informational Packets
Oct 2008: Project is currently ON HOLD. A new committee has formed...Click here for more info
Aug 2008: Project Background and Frequently Asked Questions...Click here for more info Aug 2008: Judges' Comments on jail location and jail facilities...Click here for more info
July 2008: Project Update.... Click here for more info
Timeline Purchased Property Map Aerial View
Jail Exterior
May 2008: Project Update.... Click here for more info
March 2008: Information Packet for the Eau Claire County New Jail, New Law Enforcement Center and Courthouse Remodeling Project.... Click here for more info
February 2008: The Design Phase of the Courthouse building project is underway...Click here for more info
January 2008: Due to the size and complexity of this construction project, teams have been established to work with the Design Firm...Click here for more info
November 2007: Ayres Associates has been hired by the County to perform a boundary and topographic survey of the three blocks surrounding the new jail site...Click here for more info
October 2007: Eau Claire County, in conjunction with the City of Eau Claire, are moving forward with the design and construction of the 59.1 million dollar building project as approved by the County Board in June of 2007...Click here for more info
Parking
We are making sure we have plans in place for temporary parking when construction begins. We are discussing options with local churches and with the city about leasing spaces.
Project Contact Names & Phone Numbers
Frank Draxler, Project Manager (715) 839-4919
Vacant, Assistant Project Manager
Tom Poweleit, Architect, Venture Architect (414) 271-3359
Jerry Shea, Construction Manager, Market & Johnson (715) 834-1213
|