2018 Construction Improvement Projects

Print
Press Enter to show all options, press Tab go to next option
ROAD LOCATION IMPROVEMENT ESTIMATED DATES
G Livermore to Sandy Hill 06/20/18 - 08/29/18
H S EC River Bridge to Forest Rd 2 05/16/18 - 06/14/18
HH E of CTH KK Bridge Replacement 08/01/18 - 10/01/18
I Frase Rd to CTH U 05/14/18 - 07/11/18
I STH 93 to Elm 04/09/18 - 09/17/18
K CTH HH to Trempealeau Co Pavement Replacement 05/23/18 - 08/29/18
M Hwy 12 south 2600' to Hi-Crush 07/16/18 - 08/17/18
Q 75th to CTH L Reconstruction 06/11/18 - 09/14/18
QQ .3 miles south of QS to North Shore 05/07/18 - 05/28/18