Show/Hide

Please plan your projects accordingly, and allow appropriate time for application submission and review, as well as inspection times.

The Department of Planning & Development is allowed 10 business days for the review of completed applications. Applications will be deemed complete when all forms, plans and documents required to process the application, and notification of completion of other local prerequisite permitting requirements have been received by the Planning & Development Department (SPS 320.09(11).

The Planning & Development Department is allowed 2 business days to complete inspections following the day of notification (SPS 320.10(2)(b)3.). Finally, the Planning & Development Department is allowed 5 business days to complete a final inspection following the day of notification (SPS 320.10(3)(h)2.). 

Before entering the online permit application make sure you have all required supporting documents ready to upload.

 Online Building Permit Application

Not for Land Use Permit

Click here to apply for a Land Use Permit